Demo Project - Coastal Residential House

Sample Builder Co. · Port Macquarie NSW

Contract value

$860,000

Current budget

$761,450

Forecast final cost

$768,550

Forecast margin

$110,590 (12.6%)

Commercial commentary

The sample report gives the user a practical read on budget pressure, variation exposure and the next actions needed for project review.

Budget position

Compare budget, approved changes, committed costs and forecast final cost.

Trade risk view

See which categories are contributing most to the forecast movement.

Variation control

Separate approved, pending, submitted and rejected variation movement.

Subcontract exposure

Review committed packages, claims and contractor exposure.

Key forecast movements

The sample report highlights the cost categories contributing most to the forecast movement.

TradeBudgetForecastVariance
Painting & Rendering$33,500$36,700$3,200
Hydraulic /Plumbing$37,000$39,100$2,100
Electrical$32,000$33,800$1,800
Preliminaries$48,000$48,000$0
Site Establishment$23,500$23,500$0
Concrete$66,000$66,000$0

Management suggested actions

Review forecast pressure before the next claim cycle.
Confirm pending and submitted variations before relying on final margin.
Check subcontract commitments against claims and linked variations.
Keep contingency visible so the remaining buffer is clear.

Variation position

6

Approved / invoiced

3

Pending / submitted

1

Rejected

V001 · Concrete

Slab edge thickening following engineering review

Approved

V002 · Joinery

Laundry and pantry joinery upgrade

Approved

V003 · Electrical

Additional lighting and external power points

Submitted

V004 · Hydraulic /Plumbing

Fixture relocation after selections meeting

Pending

Subcontract snapshot

12 committed packages are included in this sample, with tender and quoted packages still visible for upcoming contractor exposure.