Use these free residential construction calculators to check margin, cost to complete, contingency and variation impact using your current project figures.

No account requiredAustralian dollar formatBuilt around residential construction

Cost to complete & forecast final cost

Estimate how much cost remains on the project, then combine it with costs already recognised to see the expected final cost.

Your result

Outstanding commitments

$330,000

Uncommitted forecast

$131,150

Cost to complete

$461,150

Forecast final cost

$841,150

Committed share of cost to complete

71.6%

How it is calculated: Cost to complete = outstanding commitments plus the uncommitted forecast allowance. Forecast final cost = costs recognised to date plus cost to complete.

Use the result as a commercial check, not a substitute for the project records.

The quality of the result depends on the figures entered. Keep actual costs, outstanding commitments, variation values and remaining allowances current so the forecast reflects the job as it stands today.

Read the builder guides

Need the whole project position?

BuilderForecast keeps the calculation moving with the job.

Connect budgets, variations, materials, subcontract commitments, actual costs and cost-to-complete in one project forecast, then turn the result into a clear financial report.

Start 7-day free trial